The system enables viewing the variance in a Gantt chart tooltip when hovering over the baseline bar. The tooltip provides valuable insights into the actual project progress compared to the planned baseline.
1: Start Date Variance
The variance between the baseline start date and the actual start date
2: Finish Date Variance
The variance between the baseline finish date and the actual finish date
3: At Completion Duration Variance
The variance between the baseline duration and the actual duration at the time of completion